Wind farms Eschberg and Harsum: grid connection works and 20kV cabling - planning, tendering, project management and construction supervision 

Wind farm grid Markbygden (Sweden): Concept planning for the entire grid (400kV to 33kV)

150kV substations Gråberget and Kilberget (Sweden), 2 x 160MVA each: planning and tendering

Wind farms Gråberget, Kilberget and Snöberget (Sweden): planning / tendering of approx. 200km of 33kV wind farm cabling

Wind farm Markbygden (Sweden): planning / tendering / construction supervision of four 150kV overhead lines

 400kV substation Råbäcken (Sweden), 1825MVA: planning / tendering / project management / construction supervision

110kV substation Helmste, 63MVA: planning / tendering / project management / construction supervision

References in employment

110kV substation 31.5/40 MVA, Vydmantai, Lithuania  

110kV substation 20/30 MVA, Kraivenai, Lithuania

110kV substation 31.5/40 MVA, Narva, Estonia  

Wind farm cabling works 20kV and 100kV, Narva, Estonia

70kV substation 80/100/125 MVA, Harmignies, Belgium

Markbygden Wind Farms, Phase 1: Technical advice on the planning of the tendering process for 150kV overhead lines, 2 x 150kV substations and extension of the 400kV substation Råbäcken, Sweden, commissioned in 2013

400kV substation 1500 MVA: preliminary planning, Trolltjärn, Sweden

110kV substation 50/63 MVA, Schinne, Germany

110kv substation 31.5 MVA, Spetzerfehn, Germany

110kV substation 50/63 MVA, Neustadt, Germany

400kV substation 180 MVA, Altentreptow, Germany

110kV substation 31.5/40 MVA, Raitenbuch, Germany

110kV substation 50/63 MVA, Friesoythe Ost, Germany

110kV substation 40/50 MVA, Bagband, Germany

110kV substation 50/63 MVA, Altfunnixsiel, Germany

Renewal of a 2 x 100kW run-of-river power plant of Stadtwerke Marburg, Germany

Renewal of the district heating network of Stadtwerke Marburg incl. the construction of electric steam generators, Germany